[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107471,783,1,"单选题","在制定检验批的抽样方案时，为合理分配生产方和使用方的风险，主控项目对应于合格质量水平的α和β值均不宜超过（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",true,{"key":16,"text":17,"correct":18},"B","6%",false,{"key":20,"text":21,"correct":18},"C","8%",{"key":23,"text":24,"correct":18},"D","10%","考点:建筑工程施工质量验收基本规定。主控项目，对应于合格质量水平的α和β均不宜超过5%。参见教材P159。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]