[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107465,783,1,"单选题","在进行单位工程验收时，涉及安全和使用功能的分部工程不仅要全面检查其检验资料的完整性，而且对分部工程验收时补充进行的（ ）也要复核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","见证抽样检验报告",true,{"key":16,"text":17,"correct":18},"B","见证取样送样试验报告",false,{"key":20,"text":21,"correct":18},"C","观感质量验收报告",{"key":23,"text":24,"correct":18},"D","设计变更文件","考点:建筑工程施工质量验收程序和合格规定。所含分部工程中有关安全、节能、环境保护和主要使用功能等的检验资料应完整。涉及安全、节能、环境保护和主要使用功能的分部工程的检验资料应复查合格，这些资料与质量控制资料同等重要。资料复查不仅要全面检查其完整性，不得有漏检缺项，其次复核分部分项工程验收时要补充进行的见证抽样检验报告，这体现了对安全和主要使用功能的重视。参见教材P171。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]