[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107456,783,1,"单选题","有独特要求的项目，或复杂的、采用新工艺、新技术又缺乏设计经验的重大项目，或有重大技术问题的主体单项工程，在初步设计之后可增加（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单项技术设计阶段",true,{"key":16,"text":17,"correct":18},"B","施工图设计",false,{"key":20,"text":21,"correct":18},"C","技术设计",{"key":23,"text":24,"correct":18},"D","单项方案设计","考点:初步设计文件的编制条件。有独特要求的项目，或复杂的、采用新工艺、新技术又缺乏设计经验的重大项目，或有重大技术问题的主体单项工程，在初步设计之后可增加单项技术设计阶段。参见教材P97。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]