[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107452":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107452,783,1,"单选题","对于二次深化设计，应组织深化设计单位与原设计单位充分协商沟通，出具深化设计图纸，由（ ）审核会签，以确认深化设计符合总体设计要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","原设计单位",true,{"key":23,"text":24,"correct":14},"D","施工单位","考点:施工图设计质量管理。对于专业性较强或有行业专门资质要求的项目，如钢结构、混凝土装配式结构、幕墙等工程设计，目前多以委托具有专业设计资质的设计单位进行二次深化设计。对于二次深化设计，应组织深化设计单位与原设计单位充分协商沟通，出具深化设计图纸，由原设计单位审核会签，以确认深化设计符合总体设计要求，并对相关的配套专业设计能否满足深化图纸的要求予以确认。参见教材P100。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]