[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107451":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107451,783,1,"单选题","在工程勘察阶段，监理单位应审查勘察单位提交的勘察成果报告后，向建设单位提交（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理勘察规划",false,{"key":16,"text":17,"correct":14},"B","监理勘察方案",{"key":19,"text":20,"correct":21},"C","勘察成果评估报告",true,{"key":23,"text":24,"correct":14},"D","勘察成果修改报告","考点:工程勘察质量管理主要工作。工程监理单位审查勘察单位提交的勘察成果报告，必要时对于各阶段的勘察成果报告组织专家论证或专家审查，并向建设单位提交勘察成果评估报告，同时应参与勘察成果验收。参见教材P95～96。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]