[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107450,783,1,"单选题","监理工程师审查勘察单位提交的勘察成果报告后，应向建设单位提交勘察成果评估报告，不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","勘察工作概况",false,{"key":16,"text":17,"correct":14},"B","勘察报告编制深度",{"key":19,"text":20,"correct":21},"C","与勘察方案的符合情况",true,{"key":23,"text":24,"correct":14},"D","勘察任务书的完成情况","考点:工程勘察质量管理主要工作。勘察成果评估报告包括：勘察工作概况；勘察报告编制深度，与勘察标准的符合情况；勘察任务书的完成情况；存在问题及建议；评估结论。参见教材P96。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]