[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107432,783,1,"单选题","项目监理机构收到施工单位报送的试验室报审表后，（ ）在熟悉本工程的试验项目及其要求后对施工试验室进行审查。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理单位项目负责人",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":21},"C","专业监理工程师",true,{"key":23,"text":24,"correct":14},"D","监理单位技术负责人","考点:现场施工准备质量控制。项目监理机构收到施工单位报送的试验室报审表后，总监理工程师应组织专业监理工程师对施工试验室考核。专业监理工程师在熟悉本工程的试验项目及其要求后对施工试验室进行考核。参见教材P116。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]