[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107431":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107431,783,1,"单选题","用于工程的进口设备进场后，应由（ ）组织相关单位进行联合检查验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":18},"B","项目监理机构",true,{"key":20,"text":21,"correct":14},"C","施工单位",{"key":23,"text":24,"correct":14},"D","设备供应单位","考点:现场施工准备质量控制。联合检查由施工单位提出申请，项目监理机构组织，建设单位主持。参见教材P117。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]