[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107430,783,1,"单选题","工程项目施工前，由（ ）和项目监理机构共同对见证取样的检测机构进行考察确定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","施工单位",true,{"key":23,"text":24,"correct":14},"D","分包单位","考点:见证取样与平行检验。工程项目施工前，由施工单位和项目监理机构共同对见证取样的检测机构进行考察确定。参见教材P125。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]