[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107425":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107425,783,1,"单选题","下列报审、报验表中，需要建设单位签署审批意见的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分包单位资格报审表",false,{"key":16,"text":17,"correct":14},"B","施工进度计划报审表",{"key":19,"text":20,"correct":14},"C","分项工程报验表",{"key":22,"text":23,"correct":24},"D","工程复工报审表",true,"考点:监理通知单、工程暂停令、复工令的签发。工程复工报审表需建设单位签署审批意见。参见教材P141。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]