[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107396,783,1,"单选题","下列有关工程变更控制的表述，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总监理工程师组织专业监理工程师审查施工单位提出的工程变更申请",false,{"key":16,"text":17,"correct":14},"B","对涉及工程设计文件修改的工程变更，应由建设单位转交原设计单位修改工程设计文件",{"key":19,"text":20,"correct":21},"C","必要时，项目监理机构应建议施工单位组织设计.建设等单位召开专题会议",true,{"key":23,"text":24,"correct":14},"D","总监理工程师组织专业监理工程师对工程变更费用及工期影响作出评估","考点:工程变更的控制。选项C错误，必要时，项目监理机构应建议建设单位组织设计、施工等单位召开论证工程设计文件修改方案的专题会议。参见教材P145。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]