[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107395,783,1,"单选题","施工承包单位要求变更或修改设计图纸的某些内容时，按现行规范的规定，应向项目监理机构提交（ ）请求批准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计变更单",false,{"key":16,"text":17,"correct":14},"B","技术修改单",{"key":19,"text":20,"correct":21},"C","工程变更单",true,{"key":23,"text":24,"correct":14},"D","技术核定单","考点:工程变更的控制。工程变更单由提出单位填写，写明工程变更原因、工程变更内容，并附必要的附件，包括：工程变更的依据、详细内容、图纸；对工程造价、工期的影响程度分析，及对功能、安全影响的分析报告。参见教材P145。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]