[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107392":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107392,783,1,"单选题","对于按照规定需要验收的危大工程，施工单位、监理单位应当组织相关人员进行验收。验收合格的，经（ ）及总监理工程师签字确认后，方可进入下一道工序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位项目技术负责人",true,{"key":16,"text":17,"correct":18},"B","建设单位项目负责人",false,{"key":20,"text":21,"correct":18},"C","施工单位项目经理",{"key":23,"text":24,"correct":18},"D","专业监理工程师","考点:专项施工方案。对于按照规定需要验收的危大工程，施工单位、监理单位应当组织相关人员进行验收。验收合格的，经施工单位项目技术负责人及总监理工程师签字确认后，方可进入下一道工序。参见教材P152。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]