[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107389,783,1,"单选题","对于设计单位要求的工程变更，应由建设单位将工程变更设计文件下发项目监理机构，由（ ）组织实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","监理员",{"key":23,"text":24,"correct":14},"D","总监理工程师或专业监理工程师","考点:工程变更的控制。对于设计单位要求的工程变更，应由建设单位将工程变更设计文件下发项目监理机构，由总监理工程师组织实施。新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com 参见教材P145。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]