[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107383":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107383,783,1,"单选题","涉及主体结构及安全的工程变更，要按有关规定报送（ ）审批，否则变更不能实施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当地建设行政主管部门",false,{"key":16,"text":17,"correct":14},"B","质量监督机构",{"key":19,"text":20,"correct":21},"C","施工图原审查机构",true,{"key":23,"text":24,"correct":14},"D","建设单位主管部门","考点:工程变更的控制。如果变更涉及项目功能、结构主体安全，该工程变更还要按有关规定报送施工图原审查机构及管理部门进行审查与批准。参见教材P145。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]