[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107375,783,1,"单选题","工程设备验收前，设备安装单位应提交设备验收方案，包括验收方法、质量标准、验收依据，经（ ）审查同意后实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位负责人",false,{"key":16,"text":17,"correct":18},"B","专业监理工程师",true,{"key":20,"text":21,"correct":14},"C","施工单位技术负责人",{"key":23,"text":24,"correct":14},"D","总监理工程师","考点:现场施工准备的质量控制。工程设备验收前，设备安装单位应提交设备验收方案，包括验收方法、质量标准、验收的依据，经专业监理工程师审查同意后实施。参见教材P117。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]