[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107373":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107373,783,1,"单选题","项目监理机构收到施工单位报送的工程材料、构配件、设备报审表后，应重点审查工程材料、构配件、设备的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量证明文件",true,{"key":16,"text":17,"correct":18},"B","采购合同",false,{"key":20,"text":21,"correct":18},"C","设计要求文件",{"key":23,"text":24,"correct":18},"D","检查报告","考点:现场施工准备的质量控制。项目监理机构收到施工单位报送的工程材料、构配件、设备报审表后，应审查施工单位报送的用于工程的材料、构配件、设备的质量证明文件。参见教材P117。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]