[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107370,783,1,"单选题","用于工程的由（ ）采购的主要设备应经建设单位、施工单位和项目监理机构共同进行开箱检查。并经三方在开箱检查记录上签字，合格的方可使用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","安装单位",{"key":23,"text":24,"correct":18},"D","代理商","考点:现场施工准备的质量控制。建设单位采购的，由建设、施工、监理机构进行开箱检查，三方在开箱记录上签字。参见教材P118。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]