[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107369,783,1,"单选题","工程中采用新工艺、新材料的，应有（ ）及有关质量数据、指标，在此基础上制定有关的质量标准和施工工艺规程，以此作为判断与控制质量的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位组织的专家论证意见",false,{"key":16,"text":17,"correct":18},"B","权威性技术部门的技术鉴定书",true,{"key":20,"text":21,"correct":14},"C","设计单位组织的专家论证意见",{"key":23,"text":24,"correct":14},"D","建设单位组织的专家论证意见","考点:施工质量控制的依据。凡采用新工艺、新技术、新材料的工程，事先应进行试验，并应有权威性技术部门的技术鉴定书及有关的质量数据、指标，在此基础上制定相应的质量标准和施工工艺规程，以此作为判断与控制质量的依据。参见教材P104。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]