[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107367,783,1,"单选题","图纸会审之后，设计单位在设计文件交付施工时，需按法律规定的义务进行（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计说明",false,{"key":16,"text":17,"correct":18},"B","设计交底",true,{"key":20,"text":21,"correct":14},"C","图纸审查",{"key":23,"text":24,"correct":14},"D","图纸解释","考点:图纸会审与设计交底。在工程施工前，设计单位就审查合格的施工图设计文件向建设单位、施工单位和监理单位作出详细说明。先图纸会审，后设计交底。参见教材P109。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]