[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107366":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107366,783,1,"单选题","图纸会审的内容一般不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","图纸是否已经审查机构签字、盖章",false,{"key":16,"text":17,"correct":14},"B","设计地震烈度是否符合当地要求",{"key":19,"text":20,"correct":21},"C","节能、环保是否满足要求",true,{"key":23,"text":24,"correct":14},"D","图纸是否满足项目立项的功能","考点:图纸会审与设计交底。选项C错误，节能、环保是否满足要求是施工图审查机构审查的内容。参见教材P108～109。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]