[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107360,783,1,"单选题","设计交底会议的程序和内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计项目负责人介绍工程概况",false,{"key":16,"text":17,"correct":14},"B","各专业设计负责人进行专业设计交底",{"key":19,"text":20,"correct":21},"C","工程材料的来源是否有保证",true,{"key":23,"text":24,"correct":14},"D","设计方会同建设方将会议意见集中并形成会议纪要，经与会各单位负责人讨论确认后，在会上宣读","考点:图纸会审与设计交底。设计交底会议的程序和内容如下：【新】（1）设计项目负责人介绍工程概况。（2）各专业设计负责人进行专业设计交底。（3）设计方会同建设方将会议意见集中并形成会议纪要，经与会各单位负责人讨论确认后，在会上宣读。选项C属于图纸会审的内容。参见教材P109。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]