[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107359,783,1,"单选题","对于超过一定规模的危险性较大的分部分项工程专项方案，需由（ ）审批。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":14},"C","施工单位技术负责人",{"key":22,"text":23,"correct":24},"D","建设单位",true,"考点:施工组织设计的审查。一般情况下，由总监审核批准。建设单位仅审批超过一定规模的危险性较大的分部分项工程专项方案。参见教材P111。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]