[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107357,783,1,"单选题","施工组织设计在实施过程中，施工单位如需做较大的变更，应经（ ）审查同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","施工单位技术负责人",{"key":23,"text":24,"correct":14},"D","建设单位负责人","考点:施工组织设计的审查。施工组织设计在实施过程中，施工单位如需做较大的变更，项目监理机构应按程序重新审查。总监理工程师应及时组织专业监理工程师进行审查，需要修改的，由总监理工程师签发书面意见退回修改；符合要求的，由总监理工程师签认。参见教材P110。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]