[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107355,783,1,"单选题","施工单位按照施工进度计划完成分部工程施工，由（ ）组织相关人员对分部工程进行验收，并签署验收意见。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位项目经理",false,{"key":16,"text":17,"correct":14},"B","质量监督机构",{"key":19,"text":20,"correct":21},"C","总监理工程师",true,{"key":23,"text":24,"correct":14},"D","专业监理工程师","考点:施工质量控制的工作程序。施工单位按照施工进度计划完成分部工程施工，且分部工程所包含的分项工程全部检验合格后，应填写相应分部工程报验表，并附有分部工程质量控制资料，报送项目监理机构验收。由总监理工程师组织相关人员对分部工程进行验收，并签署验收意见。参见教材P108。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]