[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107354":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107354,783,1,"单选题","在市场采购设备质量控制中，根据设计文件，对需要采购的设备应编制（ ），以及相应的备品配件表。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采购设备表",false,{"key":16,"text":17,"correct":18},"B","拟采购设备表",true,{"key":20,"text":21,"correct":14},"C","采购计划",{"key":23,"text":24,"correct":14},"D","设备供求调查","考点:市场采购设备质量控制。根据设计文件，对需采购的设备编制拟采购设备表，以及相应的备品配件表。参见教材P197。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]