[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107353,783,1,"单选题","由总包单位或安装单位采购的设备，其采购方案须事前提交给（ ），经其审查认可。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目监理机构",true,{"key":16,"text":17,"correct":18},"B","设备总工程师",false,{"key":20,"text":21,"correct":18},"C","建设单位",{"key":23,"text":24,"correct":18},"D","设备安装工程师","考点:市场采购设备质量控制。由总包单位或安装单位采购的设备，采购前要向监理工程师提交设备采购方案，经其审查认可。参见教材P197。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]