[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107352,783,1,"单选题","下列有关市场采购设备质量控制的表述，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位负责审查总包单位编制的采购方案",true,{"key":16,"text":17,"correct":18},"B","建设单位直接采购的，施工单位要协助编制设备采购方案",false,{"key":20,"text":21,"correct":18},"C","建设单位负责审查安装单位编制的采购方案",{"key":23,"text":24,"correct":18},"D","市场采购方式主要用于非标准设备的采购","考点:市场采购设备质量控制。选项B错误，建设单位直接采购的，项目监理机构要协助编制设备采购方案；选项C错误，监理单位负责审查安装单位编制的采购方案；选项D错误，市场采购方式主要用于标准设备的采购。参见教材P197。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]