[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107340":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107340,783,1,"单选题","在设备运往现场前，项目监理机构应按设计要求检查设备制造单位对待运设备采取的防护和包装措施，并应检查是否符合运输、装卸、储存、安装的要求，以及相关的随机文件、装箱单和附件是否齐全，符合要求后由（ ）签认同意后方可出厂。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","政府质检部门",{"key":23,"text":24,"correct":14},"D","安装单位质检员","考点:设备运输与交接的质量控制。设备运输与交接的质量控制包括出厂前的检查和设备运输的质量控制。出厂前的检查：在设备运往现场前，项目监理机构应按设计要求检查设备制造单位对待运设备采取的防护和包装措施，并应检查是否符合运输、装卸、储存、安装的要求，以及相关的随机文件、装箱单和附件是否齐全，符合要求后由总监理工程师签认同意后方可出厂。参见教材P139。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]