[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107332,783,1,"单选题","监造的设备从制造厂运往安装现场前，项目监理机构应检查（ ），并审查设备运输方案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","运输安全措施",false,{"key":16,"text":17,"correct":18},"B","设备包装质量",true,{"key":20,"text":21,"correct":14},"C","海关及保险手续",{"key":23,"text":24,"correct":14},"D","起重和加固方案","考点:设备运输与交接的质量控制。为保证设备的质量，制造单位在设备运输前应做好包装工作并制订合理的运输方案。项目监理机构要对设备包装质量进行检查，并审查设备运输方案。ACD属于运输方案审查的内容。参见教材P203。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]