[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107331,783,1,"单选题","设备的购置是影响设备质量的关键环节，设备安装单位直接从市场上采购设备时，设备采购方案最终需获得（ ）批准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","设计单位","考点:市场采购设备质量控制。设备采购方案经建设单位的批准后方可实施。参见教材P197。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]