[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107271":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107271,783,1,"单选题","下列各项不是总监理工程师签发工程开工令条件的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计交底和图纸会审已完成",false,{"key":16,"text":17,"correct":14},"B","施工组织设计已由总监理工程师签认",{"key":19,"text":20,"correct":14},"C","进场道路及水.电.通信等已满足开工要求",{"key":22,"text":23,"correct":24},"D","工程资金已到位",true,"考点:项目质量控制系统的建立和实施。总监理工程师签发工程开工令，应具备下列条件：1）设计交底和图纸会审已完成；2）施工组织设计已由总监理工程师签认；3）施工单位现场质量、安全生产管理体系已建立，管理及施工人员已到位，施工机械具备使用条件，主要工程材料已落实；4）进场道路及水、电、通信等已满足开工要求。参见教材P44。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]