[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107263":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107263,783,1,"单选题","质量管理体系的认证后的整改工作中，现场审核结论就应该为“不通过”或“整改后重新申请”的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3项一般不符合",false,{"key":16,"text":17,"correct":14},"B","5项一般不符合",{"key":19,"text":20,"correct":21},"C","1项严重不符合",true,{"key":23,"text":24,"correct":14},"D","7项一般不符合","考点:质量管理体系的实施。严重不符合项只要有一项或一项以上，现场审核结论就应该为“不通过”或“整改后重新申请”；一般不符合项不管有几个，都不会影响“有条件通过现场审核”的结论。参见教材P42。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]