[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107258,783,1,"单选题","工程变更往往会对工程费用和工程工期带来影响，工程变更由（ ）审核无误后签发。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理员",false,{"key":16,"text":17,"correct":14},"B","监理工程师",{"key":19,"text":20,"correct":21},"C","总监理工程师",true,{"key":23,"text":24,"correct":14},"D","业主代表","考点:项目质量控制系统的建立和实施。工程变更由总监理工程师审核无误后签发。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]