[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107257,783,1,"单选题","工程变更往往会对工程费用和工程工期带来影响，（ ）应组织相关人员对工程变更费用及工期影响作出评估。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","建设单位",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","专业监理工程师","考点:项目质量控制系统的建立和实施。工程变更往往会对工程费用和工程工期带来影响，总监理工程师应组织专业监理工程师对工程变更费用及工期影响作出评估并组织建设单位、施工单位等共同协商确定工程变更费用及工期变化，会签工程变更单。参见教材P45。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]