[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107256,783,1,"单选题","对已进场经检验不合格的工程材料，项目监理机构应要求施工单位将该批材料（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","限期撤出施工现场",true,{"key":16,"text":17,"correct":18},"B","重新试验检测，合格后方可使用",false,{"key":20,"text":21,"correct":18},"C","就地销毁",{"key":23,"text":24,"correct":18},"D","降低标准使用","考点:项目质量控制系统的建立和实施。对已进场经检验不合格的工程材料、构配件、设备，应要求施工单位限期将其撤出施工现场。参见教材P44。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]