[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107236,783,1,"单选题","工程项目质量控制系统是以（ ）为对象，由项目监理机构负责建立的面向监理项目开展质量控制的工作体系。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程",false,{"key":16,"text":17,"correct":14},"B","分部工程",{"key":19,"text":20,"correct":14},"C","单位工程",{"key":22,"text":23,"correct":24},"D","工程项目",true,"考点:项目质量控制系统的建立与实施。工程项目质量控制系统是以工程项目为对象，由项目监理机构负责建立的面向监理项目开展质量控制的工作体系。参见教材P42。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]