[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107218,783,1,"单选题","在工程质量缺陷的处理程序中，项目监理机构签发监理通知单后的下一步程序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工单位按审查合格的处理方案实施处理，项目监理机构对处理过程进行跟踪检查",false,{"key":16,"text":17,"correct":14},"B","项目监理机构审查施工单位报送的质量缺陷处理方案，并签署意见",{"key":19,"text":20,"correct":14},"C","处理记录整理归挡",{"key":22,"text":23,"correct":24},"D","施工单位进行质量缺陷调查，分析质量缺陷产生的原因，并提出经设计等相关单位认可的处理方案",true,"考点:工程质量缺陷的处理。项目监理机构签发监理通知单后，施工单位进行质量缺陷调查，分析质量缺陷产生的原因，并提出经设计等相关单位认可的处理方案。参见教材P189。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]