[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107205,783,1,"单选题","关于项目监理机构处理工程质量事故的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签发监理通知单，要求施工单位及时处理",false,{"key":16,"text":17,"correct":18},"B","签发工程暂停令，暂停与其关联部位的施工",true,{"key":20,"text":21,"correct":14},"C","签发监理报告，向政府主管部门报告",{"key":23,"text":24,"correct":14},"D","签发工作联系单，要求施工单位及时处理","考点:工程质量事故处理。工程质量事故发生后，总监理工程师应签发《工程暂停令》，要求暂停质量事故部位和与其有关联部位的施工，要求施工单位采取必要的措施，防止事故扩大并保护好现场。同时，要求质量事故发生单位迅速按类别和等级向相应的主管部门上报。参见教材P193。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]