[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107202,783,1,"单选题","质量缺陷处理完毕后，项目监理机构应根据施工单位报送的（ ）对质量缺陷处理情况进行复查，并提出复查意见。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程停工回复单",false,{"key":16,"text":17,"correct":14},"B","工程复工回复单",{"key":19,"text":20,"correct":21},"C","监理通知回复单",true,{"key":23,"text":24,"correct":14},"D","质量事故报告","考点:工程质量缺陷的处理。质量缺陷处理完毕后，项目监理机构应根据施工单位报送的监理通知回复单对质量缺陷处理情况进行复查，并提出复查意见。参见教材P189。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]