[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107198,783,1,"单选题","工程建设过程中，下列造成工程质量缺陷的成因属于违背基本建设程序的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","无证设计",false,{"key":16,"text":17,"correct":14},"B","转包.挂靠",{"key":19,"text":20,"correct":21},"C","边设计.边施工",true,{"key":23,"text":24,"correct":14},"D","擅自修改设计","考点:工程质量缺陷的成因。基本建设程序是工程项目建设过程及其客观规律的反映，不按建设程序办事。例如，未搞清地质情况就仓促开工；边设计、边施工；无图施工；不经竣工验收就交付使用等。选项ABD均属于违反法律法规。参见教材P187。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]