[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107177":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107177,782,2,"多选题","作业分类码主要用途有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","更加方便而有效地对进度计划进行各种辅助分析",true,{"key":16,"text":17,"correct":14},"B","制作过滤器",{"key":19,"text":20,"correct":14},"C","生成项目控制过程中常用的视图",{"key":22,"text":23,"correct":24},"D","用指定代码做分组",false,{"key":26,"text":27,"correct":14},"E","加快查询的速度","ABCE","本题考查的是OraclePrimaveraP6软件。作业分类码主要用途是更加方便而有效地对进度计划进行各种辅助分析、制作过滤器、生成项目控制过程中常用的视图、加快查询的速度等，方便作业属性的进一步拓展。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]