[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107173":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107173,782,2,"多选题","工期延误计算的依据主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算公式的错误",false,{"key":16,"text":17,"correct":18},"B","合同规定的完工时间",true,{"key":20,"text":21,"correct":18},"C","施工现场情况",{"key":23,"text":24,"correct":18},"D","受干扰后实际工程进度记录",{"key":26,"text":27,"correct":18},"E","承包人呈报的经监理人同意的施工进度计划","BCDE","工期延误计算的依据主要有：①合同规定的完工时间；②承包人呈报的经监理人同意的施工进度计划；③合同双方共同认可的对工期的修改文件，如认可信、会谈纪要、来往信件等；④受干扰后实际工程进度记录，如施工日记、进度报告等；⑤施工现场情况。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]