[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107172":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107172,782,2,"多选题","工期延误的类型包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不利物质条件原因引起的工期延误",true,{"key":16,"text":17,"correct":14},"B","发包人、监理人原因引起的工期延误",{"key":19,"text":20,"correct":21},"C","长期延误和短期延误",false,{"key":23,"text":24,"correct":14},"D","不可抗力、异常恶劣的气候条件原因引起的工期延误",{"key":26,"text":27,"correct":14},"E","承包人原因引起的工期延误","ABDE","按照《水利水电工程标准施工招标文件（2009年版）》，工期延误分为发包人、监理人原因引起的工期延误，不利物质条件原因引起的工期延误，不可抗力、异常恶劣的气候条件原因引起的工期延误和承包人原因引起的工期延误4种类型。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]