[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107170":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107170,782,2,"多选题","计算工期延长的方法中，（ ）计算出的工期延长是不精确的，常引起合同争议。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","平衡点法",true,{"key":16,"text":17,"correct":14},"B","比例法",{"key":19,"text":20,"correct":21},"C","网络计划分析法",false,{"key":23,"text":24,"correct":21},"D","施工节点对比法",{"key":26,"text":27,"correct":21},"E","时标网络图法","AB","本题考查的是工期延误的计算。平衡点法、比例法计算出的工期延长是不精确的，常引起合同争议。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]