[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107169":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107169,782,2,"多选题","下列选项中属于承包人暂停施工的责任的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人违约引起的暂停施工",true,{"key":16,"text":17,"correct":14},"B","承包人擅自暂停施工",{"key":19,"text":20,"correct":21},"C","由于发包人违约引起的暂停施工",false,{"key":23,"text":24,"correct":14},"D","承包人其他原因引起的暂停施工",{"key":26,"text":27,"correct":14},"E","专用合同条款约定由承包人承担的其他暂停施工","ABDE","根据《水利水电工程标准施工招标文件（2009年版）》通用合同条款12.1款，因下列暂停施工增加的费用和（或）工期延误由承包人承担：①承包人违约引起的暂停施工；②由于承包人原因为工程合理施工和安全保障所必需的暂停施工；③承包人擅自暂停施工；④承包人其他原因引起的暂停施工；⑤专用合同条款约定由承包人承担的其他暂停施工。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]