[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107167":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107167,782,2,"多选题","工程进度影响因素中施工组织管理方面主要包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计变更等引起的资金短缺",true,{"key":16,"text":17,"correct":18},"B","设计现场服务不到位",false,{"key":20,"text":21,"correct":14},"C","管理资源问题",{"key":23,"text":24,"correct":14},"D","关键设备未到位",{"key":26,"text":27,"correct":14},"E","施工组织设计不合理","ACDE","施工组织管理方面主要体现在以下四个方面：①设计变更等引起的资金短缺；②管理资源问题：包括建设管理、设计、监理的资源不足，特别是施工单位主要人员投入不够，项目经理不到位，技术力量不足；③关键设备未到位；④施工组织设计不合理等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]