[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107166":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107166,782,2,"多选题","工程进度延误后，进度计划调整的原则有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","应从工程建设局部重要地段出发",false,{"key":16,"text":17,"correct":18},"B","进度里程碑目标不得随意突破",true,{"key":20,"text":21,"correct":18},"C","合同规定的总工期和中间完工日期不得随意调整",{"key":23,"text":24,"correct":18},"D","计划的调整应首先保证关键工作的按期完成",{"key":26,"text":27,"correct":18},"E","选择合理的施工方案和适度增加资源的投入，使费用增加较少","BCDE","工程进度延误后，进度计划调整的原则是：①计划调整应从工程建设全局出发，对后续工程的施工影响小；②进度里程碑目标不得随意突破；③合同规定的总工期和中间完工日期不得随意调整；④计划的调整应首先保证关键工作的按期完成；⑤计划调整应首先保证受洪水、降雨等自然条件影响和公路交叉、穿越市镇、影响市政供水供电等项目按期完成；⑥计划调整应选择合理的施工方案和适度增加资源的投入，使费用增加较少。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]