[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107165":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107165,782,2,"多选题","进度控制应遵循工程控制论基本原理，做好施工进度的（ ）工作。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","事前预控",true,{"key":16,"text":17,"correct":14},"B","事中监督",{"key":19,"text":20,"correct":14},"C","事后反馈纠偏",{"key":22,"text":23,"correct":24},"D","事前强化控制",false,{"key":26,"text":27,"correct":24},"E","事中控制","ABC","本题考查的是进度控制基本思想和工程进度影响因素。进度控制应遵循工程控制论基本原理，做好施工进度的事前预控、事中监督与事后反馈纠偏工作",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]