[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107164":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107164,782,2,"多选题","下列选项属于合同性进度计划的主要编制依据有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工现场的水文观测资料",true,{"key":16,"text":17,"correct":18},"B","项目路线的正确情况",false,{"key":20,"text":21,"correct":14},"C","资金供应的情况",{"key":23,"text":24,"correct":14},"D","原材料及工程设备供应情况",{"key":26,"text":27,"correct":14},"E","管理水平情况","ACDE","合同性进度计划的主要编制依据有：①合同文件（包括招标图纸、招标文件、委托合同等）；②施工现场的水文观测资料，水文地质和工程地质等勘测资料；③项目所在地区的气象、地震等有关资料；④资金供应的情况；⑤原材料及工程设备供应情况；⑥劳动力供应情况；⑦施工设备供应情况；⑧施工场地及交通运输情况；⑨供水、供电、供风和通信情况；⑩征地拆迁与移民安置情况；施工方案；管理水平情况；其他有关资料（如环境保护、文物保护和野生动物保护等）；",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]